Question

 (a) Describe the procedure to be adopted for the inspection of a safety valve fitted to an exhaust gas fired auxiliary boiler stating, with reasons, which parts should receive particularly close attention.

 (b)Describe the procedure for the setting of safety valves of exhaust gas fired auxiliary boilers.

 (c) Explain the action taken after the setting of safety valves as in (b).

 

2009/DEC        2009/FEB        2005/JUL       2012/SEP        2012/DEC        2019/APR        2019/AUG       2019/OCT