Question
With reference to the paralleling
of alternators:
Outline the principles of
synchronisation;
Explain how KW power and KVAr are shared;
for
two machines operating in
parallel explain the
consequences of EACH of the
following faults;
(i) Failure of the excitation unit of one
machine;
(ii) Sudden shutdown of one machine due to, steam
or fuel supply, shortage.
Principles
of synchronisation.
Incoming generator frequency must
be equal to the bus bar frequency.
Incoming generator voltage must be
equal to the bus bar voltage.
The incoming generator and bus bar
voltage must be in phase and in same phase rotation.
KW power. Governor
setting of alternator are adjusted to achieve KW load sharing.
kVAr Load Sharing
This is achieved automatically by
the AVR units which adjust the excitation after synchronising so that each
machine shares kVAr and generates the correct
voltage.
Excitation
failure.
When excitation is lost on a
generator the effect on the system will depend on whether it is operating
singly or in parallel with other machines.
For single operation it will be
obvious that the system voltage will collapse.
However, when one or more healthy
machines are connected in parallel, the system voltage may fall only slightly,
if at all.
This is because the excitation on
these other machines will increase and will offset any tendency for the voltage
to fall.
The faulty machine will continue to
supply kilowatts by operating as an induction generators.
Unfortunately, this reactive
current is seen as a large circulating current flowing between the faulty and
the healthy machines.
This current could eventually cause
damage to the faulty machine but, or more immediate importance, the over
current condition could cause tripping of a healthy machine.
[Failed generator will run as
induction generator drawing from the other. Rise in current in both AEs causing overcurrent trip on
failed generator and overload.
Over
current trip on other generator. ]
Failure of fuel supply
In case of steam or fuel supply
shortage the generator speed will drop frequency will drop and load will be
transferred to other generator.
In case load on 2nd generator is
more than 110% then preferential trip will occur or else overload trip will
activate and there will be total blackout i.e. depending on load on AE